Financial aid is the next functional area that will be configured. As mentioned previously, the workshops provide the technical answers for our team to then build out the system to best meet the needs specific to Acadia.

This week the project team is engaged with various colleagues and our vendor partner in completing the second workshop series on curriculum design.

The project team continues to move forward with the configuration of the Colleague Student Information system. As with all of us here at Acadia, our implementation partner, Ellucian, has moved all meetings to virtual.

The Project ACE team continues to spearhead the efforts to move the project forward. We have now re-engaged the survey process so many of you will be asked to complete one to help inform our communication and training programs.

A large group from Acadia worked with a consultant from Ellucian to establish the exacting details of Curriculum management on the new system. This effort will contribute to the success of our implementation.

The Project ACE team is delaying sending out the surveys to participants for a few weeks to allow people to adjust to the new way of working.